4115_Bates Co. Bridge Replacement - Bents 1 & 2 Cap Pours
Arrived onsite at 10:40, Contractor was finishing up from work. Concrete to be onsite at 11:00, I walked around and checked steel placement and from work.
Concrete is running late, it finally arrived at 11:42. I tested concrete. Air: 5.5%, Slump: 3-3/4", and Temp:71°. They began pouring cap for Bent 1. Made a set of 3 cylinders.
Pour went good, guys finished working concrete on bent 1 and waited for concrete for Bent 2.