4115_Bates Co. Bridge Replacement - Bents 1 & 2 Cap Pours

 

Arrived onsite at 10:40, Contractor was finishing up from work. Concrete to be onsite at 11:00, I walked around and checked steel placement and from work.










Concrete is running late, it finally arrived at 11:42. I tested concrete. Air: 5.5%, Slump: 3-3/4", and Temp:71°. They began pouring cap for Bent 1. Made a set of 3 cylinders.





Pour went good, guys finished working concrete on bent 1 and waited for concrete for Bent 2.

Bent 2 Concrete arrived at 1:53, I tested the concrete: Air: 5.5%, Slump: 6", and Temp:70°. They began bent 2 cap pour.




Bent 2 cap pour went good, Girders will be ready on May 4th. Contractor will strip forms next week and build pads for crane to set Girders.





Comments

Popular posts from this blog

4115_Bates County Bridge Replacement pile driving